A DSP-125 electric arc furnace with a liquid steel capacity of 1.15 million tonnes per year and a slab continuous casting machine with a capacity of 1.0 million tonnes per year were built.
During reconstruction of the steelmaking complex, the existing lime production facility was modernized by replacing old kilns Nos. 1 and 2 with a new shaft kiln producing 200 tonnes of lime per day.